A low utilization number tells you something is going on. It does not tell you what, and it is not a control you can pull to fix it. Tracked routinely, it is a useful early warning; managed as a target, it can drive a firm toward zero revenue. On a project, the useful version of the idea is different: plan the share of each person's week a task needs, and check who is overloaded before the work starts.
Two meanings of one word
| Firm utilization (chargeability) | Task utilization (Util%) | |
|---|---|---|
| What it measures | Billable hours ÷ total hours worked | Share of a person's 40-hour week planned on one task |
| When | After the fact, from timesheets | Before the work, in the plan |
| Who owns it | The firm, for profitability | The PM, for staffing |
| Used for | Targets and reviews | Hours, schedule and workload |
A person can be 95% chargeable and still be badly overloaded, or right on target and idle on your project. Firm utilization tells you nothing about whether your task is staffed. Keep the two apart, and never set a person's task Util% to hit a chargeability target.
Read it like a gauge
The same low utilization number can mean very different things:
- Not enough project work. The backlog is too thin to keep everyone busy.
- Too much internal distraction. Meetings, internal reports, admin and internal rework eat the week.
- Work not handed down. PMs and senior staff keep tasks themselves instead of delegating.
- A person nobody asks for. Something about how they work keeps them off project teams, and someone needs to find out what.
Each cause has its own fix: win more work, clear the internal load, delegate, or have a direct conversation. Pushing on the number itself fixes none of them.
How managing to the number backfires
- The future is non-billable. Proposals, client visits, training and mentoring don't count toward utilization. Cut them to raise the number and the backlog dries up a year later.
- Pressure to bill finds a project. Hours drift onto whatever job is open. Budgets overrun, fees get written off, and the Owner sees the invoices.
- The report stays green until it doesn't. Utilization can look healthy right up to the month the work runs out.
Routine tracking: what it does well and where it misleads
None of this means stop measuring. Tracked every month and read in context, utilization is one of the cheapest early warnings a firm has.
What it does well
- Early warning on backlog. A firm-wide or group-wide slide often shows up months before revenue does.
- Flags overload too. People sitting well above their available share for months have no room for QC, training or a bad week. That is a quality and retention risk.
- Grounds pricing. Overhead rates and multipliers assume a realistic billable share. Without the data, fee proposals rest on guesses.
- Starts the right conversations. A person's trend over several months is a fair, factual way to open a talk about workload, skills or fit.
- Costs almost nothing. It comes straight from timesheets the firm already keeps.
Where it misleads
- It shows a symptom, not a cause. The same number fits a thin backlog, internal overload, hoarded work or a staffing problem.
- It counts hours, not results. On a lump-sum job, the person who finishes under budget bills fewer hours and looks worse.
- It treats investment as waste. Proposals, mentoring and training count against it, though they build next year's work.
- It invites gaming. Individual targets push hours onto open projects and discourage handing work to others.
- It says nothing about profit. Billable hours that get written off or billed at a low rate still count as utilized.
Using it well
- Review it monthly, but read the trend over three to six months, not one snapshot.
- Look at it by group and by person, side by side with backlog, write-offs and overload.
- Use a low or high reading to ask why, then fix the cause.
- Never turn it into an individual target with pay attached.
Treat utilization the way a PM treats SPI on a monthly review: a reliable flag to go and look, not a target to hit.
Why staffing by hours alone fails
"Give the EIT 320 hours on Final Design" says nothing about when. Spread over 10 weeks it is 80% of a week; over 4 weeks it is 200%, which no one can deliver. Hours are a total. A share of the week is a rate, and only a rate can be checked against the calendar.
The arithmetic
Hours on a task = Util% × 40 hours × weeks the task runs.
Add each person's Util% across every task running in the same week. Compare the sum with the share of their time actually available for project work: after meetings, training, proposals and leave, often around 80–90%. Use your firm's own number.
Worked example
Final Design (60%) runs 10 weeks.
| Role | Util% | Hours (Util% × 40 × 10) |
|---|---|---|
| Project manager | 10% | 40 |
| Project engineer | 50% | 200 |
| Engineer in training | 80% | 320 |
| CAD designer | 75% | 300 |
| Task total | 860 |
The fee and the hours look fine. Now add the other task running in those same weeks: Permitting, with the engineer in training at 30%.
The EIT is now at 80% + 30% = 110% of a week against 85% available: 25 points over, about 10 hours a week, for ten weeks. Something will slip, and the plan already says so.
Two ways to fix it:
- Move the work. Give Permitting to the project engineer: 50% + 30% = 80%, under 85%, if nothing else of theirs runs then.
- Move the time. Stretch Final Design to 15 weeks: 320 hours ÷ (40 × 15) = 53%, plus 30% = 83%. Check that the later finish still meets the Owner's milestone.
Either way, you found the problem in the plan, not in week six.
Rules of thumb
- Nobody plans at 100% for more than a week or two. Leave room for Owner meetings, QC comments and rework.
- Senior people tend to sit at 5–15% on many tasks at once. Each looks small; add them up.
- Long and thin beats short and spiky. 40% for 10 weeks is easier to staff than 100% for 4.
- "By others" tasks, such as Owner or agency review, take no Util% from your staff, but they still hold the schedule. Keep them on it.
- Re-check the sums every time a duration changes. A task that shrinks from 10 weeks to 6 raises every Util% on it by two-thirds.
Staffing a task in five steps
- Set the task's duration from the schedule.
- List who works on it and give each a Util% for the weeks it runs.
- Let hours follow: Util% × 40 × weeks.
- Add each person's Util% across all tasks, month by month, and compare with their available share.
- Fix overloads by moving work, moving time or adding people, then check the fee still holds.
Do this in one tab. The Leroy PM Workbook runs this method with the schedule, staffing, fee and earned value tied together.